Pipeline Pigging Guide
Pipeline Commissioning:The Complete Pigging Sequence
Quick Answer
Pipeline commissioning pigging follows a 10-step sequence: (1) gauge plate run to confirm bore, (2) flood pig, (3) hydrostatic pressure test, (4–5) dewatering passes, (6–7) cleaning passes, (8–9) drying passes, and (10) gas or product introduction. Each step must be completed and verified before proceeding to the next. The sequence uses progressively firmer foam pigs escalating from low density to medium density before the final drying pass with a low density fully coated pig.
Published by Royal Poly Products
Jandakot, Western Australia
April 2026
Contents
1. What is pipeline commissioning?
2. Why pigging is central to commissioning
3. The complete 10-step commissioning pigging sequence
4. Step-by-step sequence explained
5. Gel pig commissioning sequences
6. Pre-commissioning checklist
7. Water pipeline commissioning — how it differs
8. Common commissioning pigging mistakes
9. Frequently asked questions
1. What Is Pipeline Commissioning?
Pipeline commissioning is the process of bringing a newly constructed pipeline into operational service — from the completion of construction through to the introduction of the first product and
the handover to the pipeline operator. In Australia, commissioning is governed by AS 2885 (Pipelines — Gas and Liquid Petroleum) for gas and liquid petroleum pipelines, and by the relevant state water authority standards for water transmission mains.
Commissioning is not a single event — it is a structured sequence of activities, each of which must be completed and verified before the next can begin. Pigging is central to most of these
activities. Without a correctly executed pigging sequence, a pipeline cannot be safely or legally placed into service.
The commissioning pigging sequence typically begins after hydrostatic pressure testing is complete and ends with the introduction of the first product — gas, water, oil, or other pipeline product — into a pipeline that has been confirmed clean, dry, and free of construction debris.
★ Australian regulatory requirement
Under AS 2885.3 (Pipelines — Gas and Liquid Petroleum: Operation and Maintenance), Australian pipeline operators are required to demonstrate that a new pipeline has been gauged, hydrostatically tested, dewatered, and cleaned to specified standards before it can be placed into gas or liquid petroleum service. The pigging sequence described in this guide satisfies these requirements when correctly executed and documented.
2. Why Pigging Is Central to Pipeline Commissioning
Newly constructed pipelines contain significant contamination from the construction process. This includes:
• Mill scale — a layer of iron oxide that forms on the inside of the pipe during steel
manufacturing and is present in all new steel pipelines
• Construction debris — sand, gravel, tools, temporary plugs, packaging material, and other objects left inside the pipeline during construction
• Silt and sediment from trenching, particularly in pipelines with open joints during construction
• Water from hydrostatic pressure testing — which must be completely removed before
gas or product introduction
• Residual moisture on the pipe wall — which can cause corrosion, hydrate formation in gas pipelines, or product contamination
Pipeline pigging addresses all of these contamination sources in sequence. A correctly executed commissioning pigging program removes construction debris, removes hydrotest water, cleans the pipe wall, and dries the bore to the standard required for the intended pipeline product — before the first product molecule enters the line.
★ Consequence of inadequate commissioning pigging
Pipelines that are inadequately commissioned result in debris entering the product stream — blocking regulators, meters, and valves downstream. In gas pipelines, residual moisture causes internal corrosion and hydrate formation that can block the line entirely. In water pipelines, construction debris causes water quality failures. The cost of a poorly commissioned pipeline — both in remediation and in regulatory non-compliance — far exceeds the cost of a correctly executed pigging sequence.
3. The Complete 10-Step Commissioning Pigging Sequence
The following table shows the complete commissioning pigging sequence for a new Australian gas pipeline from construction completion through to product introduction:
| Step | Phase | Pig type | Series | Objective | Success criterion | Notes |
|---|---|---|---|---|---|---|
| 1 | Pre-flood | Foam pig | LD-BR | Gauge plate run — confirm bore clear | Plate undamaged, pig intact at receiver | Fit gauge plate 95% of ID. Run before flooding. |
| 2 | Flooding | Foam pig | LD-BR | Flood pig — push water fill front | Pig arrives ahead of water front | Run with fill water to prevent air locks. |
| 3 | Hydrostatic test | None | — | Hold pipeline at test pressure | Pressure stable for test duration | No pig. Hold 4–24 hrs per AS 2885. |
| 4 | Dewatering 1 | Foam pig | LD-BR | Displace bulk test water | Large water volume at receiver | Pig may arrive degraded — inspect carefully. |
| 5 | Dewatering 2 | Foam pig | MD-BR | Remove remaining water volume | Reduced water volume at receiver | Escalate density only after bore confirmed clear. |
| 6 | Dewatering 3 | Foam pig | MD-XX | Progressive cleaning + dewatering | Minimal water, light debris | XX coating removes deposits dislodged by water. |
| 7 | Cleaning | Foam pig | MD-XX | Remove construction debris, silt, mill scale | Pig arrives with debris — note type & volume | Repeat until pig arrives clean. |
| 8 | Drying 1 | Foam pig | LD-FC | Remove residual moisture | Pig arrives damp but no free liquid | FC coating maximises liquid seal for drying. |
| 9 | Drying 2 | Foam pig | LD-FC | Final drying pass | Pig arrives dry. No visible moisture. | Pipeline ready for gas introduction. |
| 10 | Commissioning (Gas introduction) | — | — | Fill pipeline with product | Pressure, flow and quality confirmed | Pig sequence complete. Pipeline in service. |
Note that step 10 — gas introduction — is not a pig run. It is included to show where the pigging sequence ends and the operational phase begins. The pig runs are steps 1–2 and 4–9. Step 3
(hydrostatic testing) and step 10 (gas introduction) do not involve pigs.
4. Step-by-Step Sequence Explained
Step 1 — Gauge plate run (pre-flood)
The gauge plate run is the first pig run of the commissioning sequence and one of the most important. A low density bare foam pig (LD-BR) is fitted with a metal gauge plate — typically an aluminium disc with a diameter equal to 95% of the pipeline's nominal internal diameter — and run through the pipeline before any water is introduced.
The purpose is to confirm that the pipeline bore is clear of obstructions that would prevent subsequent pig runs or damage the pipeline. Any restriction, weld intrusion, or construction debris that protrudes into the bore deforms the gauge plate as the pig passes. The plate is inspected on retrieval — an undamaged plate confirms the bore is clear; deformation indicates an obstruction that must be located and removed before the commissioning sequence proceeds.
Royal Poly Products' Smart Gauge Plate service takes this further — an instrumented gauge pig that records contact data electronically during the run, allowing the exact location of any bore restriction to be identified from the data download without manual excavation along the entire pipeline length.
Step 2 — Flood pig
The flood pig is run simultaneously with the introduction of water for hydrostatic pressure testing. A low density bare foam pig is inserted into the launcher ahead of the test water, and the pipeline is then filled with water behind the pig. The pig travels ahead of the water front, preventing air from being trapped at high points in the pipeline profile.
Air pockets trapped during flooding cause inaccurate pressure test results and can lead to pressure test failure. The flood pig ensures a complete and accurate fill of the pipeline with water before the pressure test begins.
Step 3 — Hydrostatic pressure test
No pigs are run during the hydrostatic pressure test itself. The pipeline is pressurised to the test pressure specified in AS 2885 (typically 1.25 times the maximum allowable operating pressure, or MAOP) and held for the specified test duration — normally between 4 and 24 hours depending on the pipeline class and regulatory requirements.
The pipeline is inspected for leaks during the test. A successful test — stable pressure over the full test duration with no leaks — is a mandatory precondition for commissioning. Following the test, the pipeline is depressurised and the dewatering pigging sequence begins.
Steps 4 and 5 — Dewatering passes 1 and 2
Dewatering is the process of removing the hydrotest water from the pipeline using foam pig runs. The sequence begins with a low density bare foam pig (LD-BR) for the first dewatering pass, followed by a medium density bare or criss-cross pig (MD-BR or MD-XX) for the second pass.
The first dewatering pig displaces the bulk of the water volume from the pipeline to the receiver, where it is collected and disposed of appropriately. In long pipelines with complex profiles,
multiple low density pig runs may be required before the bulk water is cleared. The second pass removes the residual water that the first pig left behind at low points and in dead legs.
The volume of water recovered at the receiver after each pig run is recorded. A significant reduction in water volume between runs indicates the dewatering sequence is progressing correctly.
Steps 6 and 7 — Cleaning passes
After the bulk water is removed, cleaning pig runs are performed to remove construction debris, silt, wax, and mill scale from the pipe wall. Medium density criss-cross foam pigs (MD-XX) are the standard choice for new pipeline cleaning — they generate adequate wall contact for
effective debris removal while remaining flexible enough to negotiate the full pipeline geometry.
The cleaning sequence continues until pigs arrive at the receiver clean — no significant debris visible on the pig surface or in the receiver drain. In heavily contaminated pipelines (common in
older construction or where dust and sand have entered the line during construction), multiple cleaning passes may be required, and an escalation to MD silicon carbide (MD-SC) or wire brush pigs (MD-CW) may be appropriate if mill scale or hard deposits are present.
Each pig is inspected on retrieval. The type, volume, and nature of debris recovered gives the commissioning team a picture of the internal pipeline condition and informs decisions about
whether additional cleaning passes are required.
Steps 8 and 9 — Drying passes
After the cleaning sequence is complete, drying pig runs remove the residual moisture from the pipe wall. Low density fully coated foam pigs (LD-FC) are the standard choice for drying — the solid polyurethane shell provides the best liquid seal of any foam pig configuration, maximising water pick-up on each pass.
The drying sequence is particularly critical for natural gas pipelines, where residual moisture causes several serious problems: internal corrosion of the carbon steel pipe wall, formation of
gas hydrates (ice-like crystalline compounds that can block the pipeline entirely at low temperatures or high pressures), and contamination of the gas product stream with water vapour that fails gas quality specifications.
The drying sequence is considered complete when the pig arrives at the receiver dry — no visible moisture on the pig surface and no free liquid in the receiver drain. In some specifications, a dew point measurement of the gas introduced immediately after the drying sequence is also required to confirm the pipeline is dry to the specified moisture standard.
Step 10 — Product introduction
With the pigging sequence complete, the pipeline is ready for product introduction. For natural gas pipelines, nitrogen purging of residual air is typically performed before gas introduction to prevent the formation of a flammable gas-air mixture during the fill. The gas front is introduced progressively, monitored for pressure and flow, and the pipeline is brought up to operating pressure under controlled conditions.
The commissioning pigging sequence is now complete. The pipeline is handed over to the operator for operational service.
5. Gel Pig Commissioning Sequences
For pipelines with particularly heavy contamination — severe mill scale, significant construction debris, or pipelines where conventional foam pigs have failed to achieve the required cleanliness — a gel pig sequence can be incorporated into the commissioning program to achieve a higher standard of cleaning.
A gel pig sequence uses slugs of viscous pipeline gel pumped between foam pigs. The gel encapsulates and suspends fine debris particles — including mill scale fines and silt that foam pigs push along the bore rather than capturing — and carries them to the receiver. The following sequence is typical for a gel-assisted commissioning clean:
| Step | Product | Volume | Purpose | Notes |
|---|---|---|---|---|
| 1 | Foam pig LD-BR | 1 pig | Front pig — contains gel slug behind it | Provides a physical barrier ahead of the gel to prevent dilution by existing pipeline product. |
| 2 | Pipeline gel slug | Variable — see calc | Chemical cleaning / corrosion inhibition / dewatering | Volume calculated based on pipeline bore and length. Typically 1–3 pipeline volumes for cleaning gels. |
| 3 | Foam pig MD-BR or MD-XX | 1 pig | Rear pig — drives gel slug forward | Pushes gel through pipeline under differential pressure. Rear pig also cleans pipe wall behind gel. |
| 4 | Foam pig LD-FC | 1 pig | Drying pass after gel retrieval | Removes gel residue and any remaining moisture from pipe wall after gel run. |
Royal Poly Products supplies both the foam pigs and the pipeline gels for gel commissioning sequences, ensuring full compatibility between the gel formulation and the pig materials. The gel volume is calculated based on the pipeline bore, length, and the cleaning objective —
contact the technical team for a specific gel volume recommendation for your project.
★ When to use a gel pig sequence
Gel pig sequences are recommended when: (1) the pipeline has been open to the elements for an extended construction period and significant silt or dust contamination is expected; (2)
conventional foam pig runs have failed to achieve the required cleanliness standard; (3) the pipeline specification requires a higher than normal cleanliness standard (e.g. for chemical, pharmaceutical, or high-purity gas service); or (4) corrosion inhibitor application is required as part of the commissioning sequence.
6. Pre-Commissioning Checklist
Before beginning any commissioning pigging sequence, verify the following items are complete. This checklist is based on AS 2885.3 requirements and Royal Poly Products' commissioning
experience across Australian gas, water, and oil pipelines:
| Pre-commissioning check | What to verify | Who responsible |
|---|---|---|
| Pipeline drawings reviewed | Confirm bore diameter, wall thickness, valve types, bend radii, and any non-standard geometry along the pig run | Pipeline engineer / Royal Poly Products technical team |
| Pig specification confirmed | Pig type, density, coating, OD, and oversize percentage verified against measured internal bore | Royal Poly Products + pipeline operator |
| Launcher and receiver inspected | Barrel size, closure condition, drain valves, vent valves, and kicker line connections checked | Pipeline contractor |
| All mainline valves confirmed full-bore and open | No reduced-bore valves, no partially closed valves, no isolation valves that could trap the pig | Pipeline operator |
| Pig signalers installed at key points | Non-intrusive or intrusive signalers at launcher exit, mid-point, and receiver inlet minimum | Pipeline contractor / Royal Poly Products |
| Receiving vessel and waste management in place | Receiver drain connected to appropriate waste disposal or collection vessel for hydrotest water and debris | Pipeline contractor |
| Emergency pig retrieval plan prepared | Procedure documented for stuck pig recovery including excavation access points identified | Pipeline engineer |
| Pig run record sheets prepared | Data sheets for recording pig launch time, signaler passage times, receiver arrival time, and pig condition on retrieval | Pipeline operator |
7. Water Pipeline Commissioning — How It Differs
The commissioning pigging sequence for water transmission mains and distribution pipelines differs from the gas pipeline sequence in several important ways:
No drying requirement
Water pipelines do not need to be dried after hydrostatic testing — they will be carrying water in service. The commissioning sequence for water mains ends after the cleaning passes, without
drying pig runs. However, any disinfection or flushing requirements specified by the relevant water authority must still be completed before the pipeline is placed into potable water service.
Disinfection pigging
For potable water pipelines, a disinfection pig run using a chlorinated water slug or pipeline gel containing disinfectant may be required by the relevant water authority (Water Corporation WA, Sydney Water, Melbourne Water, SA Water, etc.) before the pipeline is approved for potable water service. This is typically performed after the mechanical commissioning pigging sequence is complete and before the final bacteriological sampling.
Material compatibility
Foam pigs and gels used in potable water pipelines must be manufactured from materials that are approved for contact with drinking water. Royal Poly Products' foam pigs used in potable
water applications are manufactured from polyurethane materials that comply with relevant Australian drinking water standards. Always specify the intended product when ordering pigs for water pipeline commissioning.
Cleanliness standards
The cleanliness standard for water pipeline commissioning is typically specified by the relevant water authority and may include requirements for turbidity, colour, pH, and bacteriological quality of flushed water samples taken at the end of the commissioning sequence. Pigging sequence adequacy is judged by whether the water quality samples meet these standards —
not simply by the visual condition of the pig on retrieval.
8. Common Commissioning Pigging Mistakes
Skipping the gauge plate run
The gauge plate run is sometimes skipped to save time or cost, particularly in short pipelines. This is a significant risk — construction debris and weld intrusions that would be detected by the
gauge plate run will be encountered by subsequent pig runs, potentially causing a stuck pig deep in the pipeline. The cost of recovering a stuck pig is always far greater than the cost of a gauge plate run. Never skip Step 1.
Running medium density pigs before bore is confirmed clear
Starting the dewatering sequence with medium density pigs before a low density bare pig has confirmed the bore is clear is one of the most common causes of stuck pigs in Australian pipeline commissioning. The low density pig may bypass partially (arriving degraded but intact) where a medium density pig would stall. Always start with LD-BR for the first dewatering pass.
Inadequate water disposal planning
Hydrotest water volumes in long pipelines can be enormous — a 20" diameter pipeline 50km long holds approximately 2,500 kilolitres of test water. Dewatering this volume requires significant waste water disposal capacity at the receiver end. Inadequate planning for test water disposal causes commissioning delays, environmental incidents, and sometimes regulatory
non-compliance. Plan water disposal before the commissioning sequence begins.
Not recording pig run data
Pig run data — launch time, signaler passage times, receiver arrival time, pig condition on retrieval, water volume recovered, debris type and volume — is required for AS 2885 compliance documentation and provides essential information for assessing whether the
commissioning sequence has been successful. Failure to record this data leaves the operator without the documentation needed to demonstrate regulatory compliance.
Declaring the pipeline dry too early
A single drying pass is rarely sufficient to dry a pipeline to the standard required for gas service. The pig may arrive dry on the surface while residual moisture remains in low points, dead legs, and rough pipe wall surface areas. The drying sequence should be continued until at least two consecutive pig runs arrive dry at the receiver — not just one.
Frequently Asked Questions
How many pig runs are needed to commission a pipeline?
A typical new pipeline commissioning sequence requires 8–12 pig runs from gauge plate run through to final drying pass. The exact number depends on the pipeline length, bore, product
type, and how contaminated the pipeline is from construction. Heavily contaminated pipelines may require additional cleaning passes. Royal Poly Products can advise on the expected number of pig runs for a specific project based on the pipeline details.
Do I need to pig a pipeline before hydrostatic testing?
Yes — a gauge plate run (Step 1) must be completed before flooding for the hydrostatic test. This confirms the bore is clear before water is introduced. Attempting to flood and test a pipeline
without first confirming the bore is clear risks damaging the pipe wall or failing the test due to undetected obstructions.
What is the correct foam pig density for dewatering after hydrostatic testing?
The first dewatering pass should always use a low density piglow density bare foam pig (LD-BR) to confirm the bore is still clear after the pressure test and to displace the bulk of the water. Subsequent dewatering passes escalate to medium density bare (MD-BR) or criss-cross (MD-XX) pigs as the water volume decreases and cleaning becomes the objective. Never start dewatering with a medium or high density pig.
How do I know when the pipeline is clean enough to begin drying?
The pipeline is ready for drying when consecutive cleaning pig runs arrive at the receiver clean — no significant debris visible on the pig surface and no significant debris volume in the receiver
drain. The decision to transition from cleaning to drying should be confirmed by a qualified pipeline engineer based on the pig inspection results. If the pig type required to achieve
cleanliness is escalating (from XX to SC or wire brush), additional cleaning runs are needed before transitioning to drying.
What is the difference between dewatering and drying a pipeline?
Dewatering removes free water from the pipeline bore — the bulk liquid volume introduced during hydrostatic testing. Drying removes residual moisture from the pipe wall surface — the thin film of water that remains after all free liquid has been removed. Dewatering uses low and medium density foam pigs to push liquid to the receiver. Drying uses low density fully coated foam pigs whose solid polyurethane shell picks up and carries residual surface moisture. Both steps are required for gas pipeline commissioning.
Can Royal Poly Products supply all the pigs for a commissioning sequence?
Yes. Royal Poly Products manufactures the complete range of foam pigs required for a gas or water pipeline commissioning sequence — LD-BR (gauge plate run and dewatering), MD-BR and MD-XX (progressive dewatering and cleaning), and LD-FC (drying passes) — as well as pipeline gels for gel-assisted cleaning sequences. Pig signalers for tracking pig passage along the pipeline are also available. Contact the team at royalpolyproducts.com/get-a-quote with your pipeline specifications for a commissioning pig schedule and quote.
Planning a Pipeline Commissioning Project in Australia?
Royal Poly Products supplies the full pigging sequence for Australian pipeline commissioning
projects — foam pigs, gel pigs, pig signalers, and technical support from our team in Jandakot, Western Australia.
About Royal Poly Products
Royal Poly Products is an Australian manufacturer of pipeline pigs and pigging solutions based in Jandakot, Western Australia. The company manufactures the full Royal Poly foam pig range — LD, ID, MD, and HD Series in bare, criss-cross, fully coated, silicon carbide, nylon wire brush, carbon steel wire brush, stainless steel wire brush, and total wire brush configurations — along with bi-directional disc pigs, cup pigs, solid cast pigs, dual diameter pigs, and pipeline gels.
ISO 9001:2015 certified and recipient of the Western Australian Export Award (Emerging Exporter 2025) and the Australian Export Award, Royal Poly Products supports pipeline operators across Australia and internationally.
Website: royalpolyproducts.com
Phone: +61 08 6117 9204
Address: Unit 5/41 Biscayne Way, Jandakot WA 6164, Australia
Email: sales@royalmechgroup.com